Ascotel IntelliGate 2025/2045/2065
Part 3 Planning DECT systems 629
Note:
Take note of safety distances and safety regulations. In areas subject to
explosion hazards take note of the relevant rules and regulations.
This important phase of the project is to be explained in greater detail using an
example.
5.4.3.1 Preparing the measurements
5.4.3.2 Global coverage in the supply range
First, ensure that the surface area of the planned supply range is satisfactorily cov-
ered.
The ideal locations for the radio units are determined using practical measure-
ments.
Factory
2 floors
warehouse /
basement
Administration
5 floors
archive/basement
Porter’s
lodge
haz0331aaena0
zone 3
zone 2
zone 4
zone 1
zone 3
zone 5
haz0347aadea0
Drawing up a situation plan:
The situation plan records approximately the
number and size of the coverage ranges required.
The measurements provide the ideal locations for
the radio units.
Radio supply and zone formation:
Create a sensible distribution, e.g. several zones in
the factory and administration (porter’s lodge, base-
ment, etc., in different zones).
Make a note of the connection capacity required
(number of simultaneous calls) for each zone to
determine the number of radio units (see also under
"Traffic density", page 633).