1. Select Yes in the Update Communication window to update the communication
configuration part in the IED.
2. Click No in the Update Communication window to keep the communication
configuration part in the IED. Other parts of the configuration will be updated.
If no changes have been done in the communication configuration
part, click No in the Update Communication window.
IEC09000729-1-en.vsd
IEC09000729 V1 EN
Figure 71: Update the communication configuration in the IED with the
configuration made in PCM600