ACS 300 User’s Manual 35
Chapter 5 - Start-up
Flowchart Commissioning Checklist
SAFETY
Read and follow the safety instructions on page v.
INSTALLATION
Check for proper grounding.
Check power wiring.
Check motor connection.
Check control wiring.
Verify availability and quality of cooling air.
PARAMETERS
Check and complete the parameter values.
TEST RUNS
Check the operation of the ACS 300 without motor.
Check the operation of the ACS 300 with motor connected.
Check external controls and emergency stop.
Check the rotation direction.