EasyManua.ls Logo

ABB ACS 6000 - Cold Commissioning; Hot Commissioning; Commissioning Report

ABB ACS 6000
62 pages
To Next Page IconTo Next Page
To Next Page IconTo Next Page
To Previous Page IconTo Previous Page
To Previous Page IconTo Previous Page
Loading...
Chapter 1 - Overview
ABB
10 (of 62) 3BHS135824 ZAB E01Rev. D ACS 6000 Commissioning Manual
Typically, commissiong has two parts, i.e. so called "Cold"- and "Hot"-
commissioning.
Cold Commissioning
Spare parts available
Internal cabling, auxiliary voltage, converter cooling system
Drive I/O, insulation resistance measurements, MCB
SW parameterisation, no-load- tuning and running tests
Hot Commissioning
Spare parts available
Coupling test: integrated tests with the automation system
Load tests: tuning controllers, mechanical operation and heat run
Additional work for the drive commissioning engineer (if so
agreed):
Commissioning of the motor / transformer
Commissioning of MCB / protection relays
Adjusting and tuning of external devises (like sensors, switches)
1.8 Commissioning Report
While commissioning the ACS 6000, the commissioning report must
be filled out. After the commissioning this report must be mailed to
mv.ac.supportline@ch.abb.com.
Parameter and back-up file(s) must be:
1 stored with DriveWindow, and if possible also with DriveDebug,
PC-tool,
2 attached to the commisioning report,
3 printed out and filed in the ACS 6000 User’s Manual on site.
In addition to the above mentioned commissioning report also the
internal field service report must always be filled out. In this internal
service report the following summary and data needs to be given:
Open items
Deviations to standard commissioning time
Drive tuning report (pictures), tuning problems
Special problems, experiences, etc.

Table of Contents

Other manuals for ABB ACS 6000

Related product manuals