8 (of 62) 3BHS135824 ZAB E01Rev. D ACS 6000 Commissioning Manual
1.5 Preparation for Commissioning (Project Management Input)
Preparatory steps must be taken and data must be collected before
the commissioning is started.
Make sure that the following list is fulfilled:
Motor parameters are available.
Pre-setting of parameters is available.
Commissioning spares are available or sent.
Tools according to the list are available.
Special tuning instructions are available.
Commissioning program is available.
Instructions for commissioning is received.
Preparative work for possible drive upgrade is done.
Latest updates of SW is received.
1.6 Preconditions for Commissioning
The following preconditions must be fulfilled before the commissioning
of the drive can start.
NOTE! The item 7, ie. insulation test of cables, transformers and
motor, can be made by the commissionig engineer. In that case, one
additional day (per motor – drive combination) needs to be reserved.
After insulation test the mains cables can be connected, except at
converter end.
General Preconditions
1 The Installation of the ACS 6000 must be completed according to
the ACS 6000 User’s Manual Chapter 8 – Mechanical Installation
and Chapter 9 – Electrical Installation.
Shortly these installation requirements are the following:
Deionised water available on site and raw water connections
ready
Auxiliary supply voltage available and related cable
connections ready. The permission to switch on the auxiliary
voltage must always be granted by the commissioning
engineer (ref. 5.2)!
Drive mechanical installation ready
External wiring from and to the converter ready
High Voltage Equipment
2 High voltage (HV) switchgear is installed, connected and ready
for operation.
3 Converter transformer is installed, connected and ready for
operation.