24 Introduction to the manual
Quick installation and commissioning flowchart
Task See
Identify the frame of your drive: R1…R9. Operation principle and hardware description:
Type designation key on page 40
Plan the installation: select the cables, etc.
Check the ambient conditions, ratings and
required cooling air flow.
Planning the electrical installation on page 65
Technical data on page 159
Unpack and check the drive. Mechanical installation: Frames R1 and R2
cable box (IP21, UL Type 1) on page 48,
Unpacking and examining delivery, frames R1
and R2 on page 47, Unpacking and examining
delivery, frames R6…R9 on page 52
If the drive will be connected to an IT
(ungrounded) system, check that the internal
EMC filter and ground-to-phase varistor are
not connected. If the drive will be connected to
a corner-grounded TN system, check that the
internal EMC filter is not connected.
Operation principle and hardware description:
Type designation key on page 40
Electrical installation: Checking the
compatibility with IT (ungrounded) and corner-
grounded TN systems on page 91
Install the drive on a wall. Mechanical installation on page 43
Route the cables. Planning the electrical installation: Routing the
cables on page 78
Check the insulation of the input cable and the
motor and the motor cable.
Electrical installation: Checking the insulation
of the assembly on page 90
Connect the power cables. Electrical installation: Connecting the power
cables on page 96
Connect the control cables. Electrical installation: Connecting the control
cables on page 116
Check the installation. Installation checklist on page 139
Commission the drive. ACS580 standard control program firmware
manual (3AXD50000016097 [English])