PE,
L1, L2, L3, T1/U, T2/V, T3/WFrame size
lbf·ftN·mlbf·ftN·mlbf·ftN·m
0.91.27.29.82230R6
0.91.27.29.83040R7
0.91.27.29.83040R8
0.91.27.29.85270R9
Detaching and reinstalling the connectors
This is possible but not recommended.
Terminals T1/U, T2/V and T3/W
• Remove the nut that attaches the connector to its busbar.
• Put the conductor under the connector pressure plate and pre-tighten the
conductor.
• Put the connector back to its busbar. Start the nut, and turn it at least two
rotations by hand.
WARNING!
Before using tools, make sure that the nut/screw is not cross-threading.
Cross-threading will damage the drive and cause danger.
• Tighten the nut to a torque of 30 N·m (22 lbf·ft).
• Tighten the conductor(s) to 40 N·m (30 lbf·ft) for frame R8 or to 70 N·m
(52 lbf·ft) for frame R9.
Terminals L1, L2 and L3
• Remove the combi screw that attaches the connector to its terminal post,
and pull the connector off.
• Put the conductor under the connector pressure plate and pre-tighten the
conductor.
156 Electrical installation – Global (IEC)