Introduction to the manual 25
Quick installation, commissioning and operation
flowchart
Task See
Plan the electrical installation and acquire the accessories needed
(cables, fuses, etc.).
Check the ratings, required cooling air flow, input power connection,
compatibility of the motor, motor connection, and other technical
data.
Guidelines for planning the
electrical installation (page 69)
Technical data (page 163)
Check the installation site. Ambient conditions (page 173)
Unpack and check the drive (only intact units may be started up).
Make sure that all necessary optional modules and equipment are
present and correct.
Mount the drive.
Mechanical installation (page 55)
If the drive has been non-
operational for more than one year,
the DC link capacitors need to be
reformed (page 155)
Route the cables. Routing the cables (page 79)
Check the insulation of the supply cable, the motor and the motor
cable.
Checking the insulation of the
assembly (page 89)
If the drive is about to be connected to an IT (ungrounded) system,
check that the drive is not
equipped with EMC filter (option +E202).
Checking the compatibility with IT
(ungrounded) systems (page 90)
Connect the power cables.
Connect the control cables.
Electrical installation (page 89),
Check the installation. Installation checklist (page 123)
Start the drive up. Start-up (page 125)
Operate the drive: start, stop, speed control etc. ACS880 quick start-up guide,