42/24-10 EN Rev. 9 Chapter 4: Electrical Connection 4-13
Signal, Control and Interface Line Connection
CAUTION!
Follow local regulations on installing and connecting electrical wiring.
Locate the signal, control and interface lines separately from the power supply
lines.
Locate the analog and digital signal leads separately from each other.
Carefully plan the arrangement of signal lines in the cables as well as the use of
connector box openings in the IP-54 system housing.
What materials are
needed?
Selection of the required conductors depends on line length and planned
current load.
Notes regarding conductor section for I/O module connection:
The maximum capacity of terminals for stranded or solid conductors is 1 mm
2
(17 AWG).
The stranded conductor may be tinned on the tip or twisted for simplified
connection.
When using wire end ferrules the total section should not exceed 1 mm
2
,
i.e. the maximum stranded conductor section is 0.5 mm
2
. The Weidmüller
PZ 6/5 crimping tool must be used for crimping the ferrules.
Maximum line length 1200 meters (3940 feet, transmission rate max. 19200 bit/s)
for RS485.
Maximum line length 15 meters (50 feet) for RS232.
The matching female connector housings for the connection strips on the I/O
modules are supplied with the device.
Connection Box The IP-54 version of the system housing has a connection box on the back of the
electronics module.
The connection box has:
EN version: Five M20 and two M32 threaded cable connections
CSA version: One 1-1/4-inch and two 3/4-inch conduits.
Two M32 threaded cable connections are provided to route system bus, Modbus,
Profibus and Ethernet cables.
Protective Cap A protective cap is factory-installed on the rear of the electronics module when the
Limas11 UV analyzer module is installed in the central unit.
It is imperative to re-install the protective cap after connection of the electrical
lines! Otherwise light penetration during operation may lead to erroneous measure-
ment values and measurement range overflows.