EasyManua.ls Logo

ABB Conceptpower DPA 500 - Page 20

ABB Conceptpower DPA 500
81 pages
To Next Page IconTo Next Page
To Next Page IconTo Next Page
To Previous Page IconTo Previous Page
To Previous Page IconTo Previous Page
Loading...
04-3275_OPM_ABB_CONCEPTPOWER_DPA_500kW_EN_REV-A.docx Page 20/78 ABB
Modifications reserved
The AC wiring must be done in the following order:
1. Connect first the PE wire coming from the LV Distribution Board (mains) to the terminal labelled "PE".
(for simplicity only the bottom cable entry is shown here, the bars for top entry are positioned the
same but mirrored bottom-top)
Bottom cable entry Top cable entry
2. SINGLE INPUT FEED - Connect the input wires 3-phases + N coming from the LV Distribution Board
(mains), by referring to the table here below. Keep the phase rotation in clock-wise sense.
MAINS INPUT CABLE
UPS BUSBAR
Phase L1
1-L1
Phase L2
1-L2
Phase L3
1-L3
NEUTRAL
N
EARTH
PE
Bottom cable entry Top cable entry

Table of Contents

Other manuals for ABB Conceptpower DPA 500

Related product manuals