Operation Manual / TPS44-F.. - TPS61-F..
Maintenance
5
Turbine cleaning during operation
5.3
Page 63
© Copyright 201
6 ABB. All rights reserved.
September 2016 HZTL2412_EN Revision F
Recommended operating state for turbine wet cleaning
The following operating state has been tested and is approved by ABB
Turbo Systems:
Characteristic / component
Conditions
short
water injection time
long
water injection time
Engine load (guide value)
2040 %
Turbine inlet temperature
T
TE
before water injection
350 - 400 °C 350 - 430 °C
Water supply
ensured
Water pressure (overpres-
sure over atmosphere) p
WT
2.0 bar 1.5 bar
If necessary, engine performance must be reduced to maintain these
conditions.
The cleaning cycle can now be started based on the following description.

Table of Contents

Other manuals for ABB HT842025

Questions and Answers:

Question and Answer IconNeed help?

Do you have a question about the ABB HT842025 and is the answer not in the manual?

ABB HT842025 Specifications

General IconGeneral
BrandABB
ModelHT842025
CategoryIndustrial Equipment
LanguageEnglish

Related product manuals