Refitting, battery
Use this procedure to refit the SMB battery.
NoteAction
DANGER
Turn off all:
• electric power supply
• hydraulic pressure supply
to the robot, before entering the robot working
area.
1
ELECTROSTATIC DISCHARGE (ESD)
The unit is sensitive to ESD. Before handling the
unit please read the safety information in the sec-
tion The unit is sensitive to ESD on page 34
2
Clean the joints that have been opened. See Cut
the paint or surface on the robot before replacing
parts on page 219
3
Art. no. is specified in Required
equipment on page 189.
Reconnect the battery cable and install the battery
pack into the SMB/battery recess.
Note
RMU batteries are installed together with a battery
holder to be properly secured inside the recess.
See figure.
4
Shown in figure Location of SMB
battery on page 188.
xx1300000307
A Battery pack RMU
B Battery holder
C Battery cable
D Strap
Strap the battery cable to the holder.
Shown in figure Location of SMB
battery on page 188.
Secure the SMB battery cover with its attachment
screws.
5
Seal and paint the joints that have been opened.
See Cut the paint or surface on the robot before
replacing parts on page 219
6
Detailed in chapter Calibration -
section Updating revolution coun-
ters on page 444.
Update the revolution counters.7
Continues on next page
Product manual - IRB 6640 Foundry Prime 191
3HAC040586-001 Revision: N
© Copyright 2011-2018 ABB. All rights reserved.
3 Maintenance
3.4.8 Replacing the SMB battery
Continued