Mechanical installation procedure
1. Examine the delivery for damage.
2. Unpack the delivery.
3. Make sure that the delivery is correct.
4. Make sure that the installation area is suitable and ready.
Refer to Technical data on page 123 and Required installation clearances on
page 132.
5. Install the wall-mounting plate.
6. Move the unit to the installation area.
7. Lift the unit onto the wall-mounting plate.