3.3. Set the Host IP as the PMU IP address configured for the port in use. Here
the LANAB:1 IPAddress (192.168.1.10) is set.
3.4. Set the Port as the TCP port defined in the PMU for control of data sent
over UDP client group 1 (Default value: 4713). This can be found under the
parameter TCPportUDPdataCtrl1 as one of the UDP communication
parameters.
3.5. Save the Alternate Command Channel Configuration settings.
3.6. Continue to the section
Verifying the IEEE C37.118/1344 UDP
communication
11.5 Verifying the communication
GUID-D10769FC-6C70-48A3-A1D8-FAFCCA82A3BE v2
Connect your PC to the substation network and ping the connected IED and the
Substation Master PC, to verify that the communication is working (up to the transport
layer). Make sure that the optical fibers are connected correctly.
After checking the communication, it is time to verify the IEEE C37.118/1344
communication over both TCP and UDP protocols.
One way to verify the communication up to the application layer is to use a protocol
analyzer connected to the substation bus, and monitor the communication.
Alternatively, the PMU Connection Tester tool can be used to verify the IEEE
C37.118/1344 communication. The section
Setting the TCP/UDP client
Section 11 1MRK 502 073-UUS A
Establishing connection and verifying the IEEE C37.118/1344 communication