EasyManua.ls Logo

ABB Relion 615 series - Replacing a SPA 300 Series Relay in 19 Rack by a 615 Series IED

ABB Relion 615 series
84 pages
To Next Page IconTo Next Page
To Next Page IconTo Next Page
To Previous Page IconTo Previous Page
To Previous Page IconTo Previous Page
Loading...
11
22
GUID-A8741360-1066-494D-9340-3DA0AF81E778 V1 EN
Figure 37: Installation plate for replacing SPA 300 relay
1
Installation plate
2 Torx head screw M5x10
4. Tighten the screws.
5. Mount the new IED.
Use a raising frame if needed.
For ordering numbers, see the ordering number table.
4.3.16 Replacing a SPA 300 series relay in 19" rack by a 615
series IED
Mount the IED with the mounting frame to the panel cut-out according to the
rack mounting instructions.
No modifications are needed to the panel.
For replacement kit ordering numbers, see the ordering number table.
Section 4 1MRS756375 K
Mounting
50 615 series
Installation Manual

Table of Contents

Other manuals for ABB Relion 615 series

Related product manuals