Figure 472: Connection diagram for current circuit supervision with two sets of
three-phase current transformer cores (protection and measurement)
Example of incorrect connection
The currents must be measured with two independent cores, that is, the phase
currents must be measured with a different core than the reference current. A
connection diagram shows an example of a case where the phase currents and the
reference currents are measured from the same core.
Supervision functions
1MRS757644 H
882 620 series