IEC140000143-1-en.vsd
IEC140000143 V1 EN-US
Figure 15: Stop capturing the IEEE C37.118 synchrophasor data
Open the capture file and observe the captured synchrophasor data. In order to get the Phasor
names on top of each column (See figure
16), the capture process should start before connecting
the PMU Connection Tester to the PMU, i.e. first start the capturing and then click Connect.
1MRK 504 165-UUS Rev. J Section 9
Establishing connection and verifying the IEEE C37.118/1344 communication
Transformer protection RET670 77
Commissioning manual