GUID-2EAD9C28-6C56-4CB4-8CF7-7B0621A7DCDC V2 EN
Figure 25: Importing example configurations
8. On the Version selection page, select the IEC 61850 version and click Next.
Regardless of the protocol used in the installation for each
project, the IEC 61850 version must be selected when adding the
first protection relay to the plant structure. After the initial
selection all protection relays in the plant structure use the
selected version, either Edition 1 or Edition 2.
9. The Setup complete page shows the summary of the protection relay's IED type,
version, IP address and the selected order number. Click Finish to confirm the
configuration and conduct the insertion.
Section 4 1MRS757810 C
Setting up a project
48 REC615 and RER615
Engineering Manual