Operation Manual / TPL73-B.. - 85-B11/ -B12
5 Maintenance / 5.4 Cleaning the compressor during operation
© Copyright 2018 . All rights reserved. HZTL2480_EN Revision D July 2018
Operating the cleaning
medium vessel
u Fulfil operating state prerequisites for cleaning compressors with
XC4 without fail before cleaning.
u Open cover (05) of cleaning medium vessel (01).
u Fill with clean water.
u Screw down cover (05).
u Open valve (06) for about 3 minutes.
u Close valve (06) and check that all water has been sucked out.
u After cleaning, wait at least 5 minutes with engine running to allow
turbocharger to dry.
If the cleaning operation is not satisfactory, it may be repeated up to
two times.
If the cleaning result is still not satisfactory after three attempts and the
engine values are also unsatisfactory, we recommend that you have the
turbocharger inspected and cleaned by an official ABB Turbocharging
Service Station.
Cleaning parameters per turbocharger compressor
Product Content of water vessel [dm
3
]
TPL73-B 2.0
TPL77-B
TPL80-B 3.0
TPL85-B
Page 66 / 151