5 - Installation
During installation do not
place the inverter with the
front cover
05
facing the
ground.
Install the inverter by following this
procedure:
Place the bracket
01
perfectly level
on the wall and use it as a drilling
template.
The selection of the appropriate
number and distribution of the an-
chors is the responsibility of the in-
staller. The choice must be made
according to the type of wall, frame
or other type of support, and should
be sized considering a total load of
more than 4 times the weight of the
inverter (total 4x20.5 = 82 kg total).
Depending on the type of anchor
chosen, drill the holes required for
the xing of the bracket
01
(Figure
A
).
Fix the bracket
01
to the wall or
structure
Carefully lift the inverter and hook
it to the bracket
01
by inserting the
two supports in the slots on the in-
verter (Figure
B
).
Proceed to anchor the inverter to the
bracket by pressing the lower part
toward the wall or structure until the
two springs
02
on the bracket
01
set
the inverter in position (Figure
B
).
Wall mounting
A
B