Installation, Maintenance and Commissioning Manual :6877419 02/2013
Commissioning procedure
Indicate on the commissioning sheet how the water is fed to the unit.
• Mains
• Feed tank
• Supply water pressure
Indicate what features are fitted to the installation.
• Water strainer
• Shut off valve
Indicate on the commissioning sheet information regarding the humidifier bottle
• Type
• Size
• Code
(e.g. BL0T3A00H0)
Measure the following information whilst the humidifier is operating.
• Conductivity
• Current L1,L2 and L3
1 Amp current approximates to about 1kg/hr of steam output.
Ensure that the humidifier solenoid valve operates in the following states. Record on
commissioning sheet.
• Fill
• Drain
Check that the humidifier drain is operating satisfactory and that there are no leaks.
Check the fan operation on the condenser or dry cooler is correct. Record on the
commissioning sheet the following information.
• Correct rotation
• Motor current L1, L2 and L3 (AC Fans only)
• Fan Speed
Record on the commissioning sheet the following
• Flow rate
• Pressure drop
Commissioning