Installation, Maintenance and Commissioning Manual :6877419 02/2013
Maintenance
rained competent personnel.
The equipment contains live electrical and moving parts, ISOLATE prior to
maintenance or repair work.
Gas Regulation checks are carried out at the appropriate pe
The maintenance schedule indicates the time period between maintenance operations.
At every service visit the following checks should be carried out:
1 Examine the fan and motor assemblies for lateral and end play in the bearings.
2 Ensure that no water is entering the motor via the electrical gland plate.
3 Check fan blades for damage and corrosion.
1 Visually examine pipework and components for damage, wear and tear and oil
patches, the latter being indicative of a system leak.
2 Ensure the fan head pressure controller is controlling the head pressure at the
required setting as indicated on the commissioning sheets provided.
The gauges can then be removed from the system. Do not forget to replace the security
caps on the Schrader valves.
Clean the condenser coil with a stiff bristled hand brush. If dirt has accumulated over a
long period or the coil is greasy or sticky, then it may be necessary to use a water hose or
chemical pressure hose. Take care not to damage the fins and comb out if they have
become damaged in any way.
For epoxy coated coils use a suitable cleaning fluid and soft bristle brush.
eam for cleaning condenser coils otherwise damage or danger may
result from excessive internal pressures
1 Check all electrical connections for signs of overheating or arcing.
2 Check all cables for signs of chafing or physical damage.
1 Clean the cabinets using a mild detergent.
2 Treat any paint damage or rust as necessary.
As per 3 months plus the following:
1 Check all electrical connections for security.
2 Check all refrigeration connections with a leak detector.
OUTDOOR