Main task Chapter number Subtask [section/page]
Stand alone tests
(NE tests)
7 “Preparation and test of the main unit” (p. 7-6)
“E1 tributary ports distribution wiring test” (p. 7-7)
“Line port connection to optical distribution frame test”
(p. 7-9)
“PDH option card test” (p. 7-13)
“Optical STM-1 option card test” (p. 7-16)
“X.21 option card test” (p. 7-19)
“X4IP, X8PL, and X5IP option card test” (p. 7-22)
“X12SHDSL-V2 option card test” (p. 7-25)
Link acceptance
tests
8 “Connecting the fiber cables” (p. 8-2)
“Remote login test” (p. 8-4)
“BER test” (p. 8-6)
General information
Sequence of steps
...................................................................................................................................................................................................................................
2-18
Alcatel-Lucent - Proprietary
See notice on first page
365-312-802R7.2