2018 FORD F-150 5.0L COMPRESSED NATURAL GAS CONVERSION SYSTEM INSTALLATION INSTRUCTIONS
2018 F-150 5.0L INSTALLATION MANUAL
Page 3
Check List:
1. Conrm packing slip to insure that you have received all components, assemblies, and sub-assemblies.
2. Make sure none of the components and assemblies have been damaged during shipping.
3. Pre-inspect the vehicle following the QVM, Q-185, and NFPA 52 regulations (Contact ALTECH-ECO for the inspection check list).
4. Begin your conversion process.
• Cylinder Installation
• Regulator assembly installation
• Fuel ll installation
• High pressure line installation and routing
• Low pressure and coolant line installation and routing
• Underhood installation
• Wiring (Including switch and gauge) Installation
• Decal placement
• Fill and leak test
• Begin your QC Process
5. Check tire pressure before test driving.
6. Check and ll coolant uid before starting and test driving.
7. Be sure the rear harness is routed properly and that there is no loose hanging wires under the vehicle.
8. Be sure all provided parts are installed.
9. Perform nal test drive.
THIS DOCUMENT CONTAINS PROPRIETARY DATA OF ALTECH-ECO AND
SHALL NOT BE USED OR DISCLOSED IN WHOLE OR IN PART TO DESIGN
OR FABRICATE ANY PRODUCT FOR ANY PURPOSE, OR REPRODUCED
OR TRANSMITTED TO ANY OTHER ORGANIZATION WITHOUT WRITTEN
PERMISSION FROM ALTECH-ECO CORPORATION.