Gree GMV6 DC Inverter VRF Units Service Manual
15
Checklist Before GMV6 Commissioning
Category No. Item Reference Value Qualified Inspector
Refrigerating
system
16
The inclination of indoor and
outdoor branch joints should not
exceed the specified requirements.
Branch joints need to be
installed horizontally. Refer
to branch joint installation.
17
Is the stop valve of each module
open to the maximum opening?
18
Is the refrigerant pressure normal?
Connect the high pressure gauge of
the pressure gauge to the liquid
pipe valve of the outdoor unit,
connect the low pressure gauge to
the gas pipe valve, and read the
value.
At this time, the high and low
pressures of the system are
in balance, and the
difference between the
saturation temperature
corresponding to the
balanced pressure value and
the ambient temperature
(higher one of the indoor and
outdoor temperatures) does
not exceed 5°C. If it exceeds
5°C, check for the outdoor
unit leakage.
19
Is there any leakage of chiller oil at
the valve?
If so, immediately check for valve
leakage with soap bubbles or a leak
detector. If leakage is confirmed,
stop subsequent commissioning at
once, and continue the work only
after the problem is solved.
20
Is the outdoor unit being warmed up
for more than 2 hours before
commissioning?
Electrical
system
21
Is the power cable connected
correctly? Is the terminal block
secure?
22
Is the power cable appearance in
good condition and not exposed?
The appearance is in good
condition and not exposed.
23
Is the power capacity less than the
maximum power of the unit?
The power capacity is not
less than the maximum
power of the unit.
24
Is there any poorly connected
electrical component detected
when the power is off?
All components are reliably
connected.
25
Do the cable diameters of the
indoor and outdoor units meet the
unit design requirements?
Refer to electrical
installation.
26
Do the circuit breaker and leakage
switch meet the unit design
requirements?
Refer to electrical
installation.
27
Do the power voltage, phase
sequence, and frequency meet the
unit requirements?
The power voltage, phase
sequence, and frequency
are consistent with those on
the unit nameplate, and the
voltage fluctuates within
±10%.
28
Is the power cable more than 1 m
away from a TV?