3. Ceiling elements
1. Place the first ceiling element on top of prefiously installed and fixed wall elements (Figure
3a). Check walls for vertical level. Ceiling element must sit flush with walls external layer
and with no excessive gaps between internal panels. Fix with screws.
2. Place the second ceiling element on top of walls with approx. 10mm gap with previous
ceiling and slide into place. Attach additional plywood support pieces on the joint between
ceilings. Fix with screws around.
NOTE! Do not support elements on edge of previous installed element!
Figure 3a.
CE1
CE2