ACS 653, ACS 663 Service Manual
SP00D00624 2021-04-08 Robert Bosch GmbH
24
Introduction

7. Remove the 2 screws (3) and remove the
ush port manifold.
8. Fix the N2H2 manifold by mean of the
2 screws (3).
1
1
1
2
2



For the magnet installation, refer to Figure 1-19.
1. Plug the magnet (1) within the housing
underneath the machine base.
For fix the calibration weight, refer to
“Calibration check” in this section.
1


3
3
6
5
S20
S19
4
9. Disconnect rilsan hose from tting (4) of the
injection manifold and connect it to tting (6)
of N2H2 manifold.
10. Connect the rilsan hose coming with the kit
within tting (5) of N2H2 manifold and tting
(4) of the injection manifold.
11. Connect faston S19 and S20 of solenoids
harness to the solenoids on N2H2 manifold.
12. Insert the rear cover so that the 4 holes on
the sides the cover t into the 4 clips on the
machine. Push down to hook the rear cover.
13. Close the service rear door.
14. Reinstall the plastic frontal cover and
x it by 6 screws (1) and the 2 ones (2)
(see Figure 1-16).
15. Attach the outside high- (red) and low-side
(blue) service hoses. Tighten at 7.9 Nm torque.
16. Switch on the machine.
17. Call up the Main Menu.
18. Select  icon.
19. Select  icon.
20. Select  " "
and .
21. Perform a functional test and check for leaks.