66 | Fitting
UNIMAT6 720 807 794 (2013/04)
10 Fitting
10.1 Transport and handling
10.1.1 Delivery method and transport options
The UNIMAT UT-L boiler and UNIMAT UT-L boiler with
integrated heat exchanger are each delivered in a
transport unit.
Transport
To transport the boiler block with a crane, only use the
two lifting eyes. These are fitted at the top of the boiler
pressure body, at the front and back.
The use of rollers underneath the base frame to
transport the system at floor level is not permitted.
There is a danger that the base frame will become
warped.
10.1.2 Handling dimensions
For handling the boiler, it is essential to size the
entrance to the installation room slightly larger than the
boiler dimensions. See tab. 29 for the minimum handling
dimensions.
Entrance
UNIMAT UT-L boiler UNIMAT UT-L boiler
UNIMAT UT-L boiler with flue gas
heat exchanger
Boiler size Minimum width Minimum height Minimum width Minimum height
[mm] [mm] [mm] [mm]
UT-L 1 1400 1850 1500 1865
UT-L 4 UT-L 2 1550 2000 1650 2015
UT-L 10 UT-L 6 1650 2100 1755 2115
UT-L 14 UT-L 8 1750 2200 1855 2215
UT-L 18 UT-L 12 1800 2250 1910 2265
UT-L 24 UT-L 16 1900 2350 1995 2365
UT-L 28 UT-L 20 1950 2400 2060 2415
UT-L 30 UT-L 22 2050 2500 2155 2515
UT-L 34 UT-L 26 2150 2600 2250 2615
UT-L 40 UT-L 32 2350 2800 2435 2800
UT-L 42 UT-L 36 2500 2950 2605 2950
UT-L 46 UT-L 38 2650 3100 2750 3100
UT-L 50 UT-L 44 2800 3300 2905 3250
UT-L 54 UT-L 48 2950 3400 3045 3400
UT-L 58 UT-L 52 3120 3650 3240 3600
UT-L 60 UT-L 56 3450 3950 3555 3900
UT-L 64 UT-L 62 3650 4150 3750 4100
Table 29 Minimum handling dimensions for UNIMAT UT-L boilers; the dimensions specified are recommended values and