7
We reserve the right to make any changes due to technical modifications.
Installation and maintenance instructions Logano GE315 • Issue 02/2006
2Installation
2 Installation
2.1 Standard delivery
The Logano GE315 boiler can be supplied as ready
assembled block or in individual boiler segments.
2.1.1 Pre-assembled delivery
1 Pallet: Boiler block
with burner door and feed pipe
1 Cartons: Casing
(depending on boiler size)
1 Foil packaging: Thermal insulation
2.1.2 Supplied in sections
1 Pallet: Front and rear segment
3 central segments and burner door
1 Pallet: Central segments – depending on boiler
size
1 Carton: Mounting components and flue gas
collector
1 Bundle: Tie bars and return header
1 Cartons: Casing
(depending on boiler size)
1 Foil packaging: Thermal insulation