8200-M698-O1 Rev B 225 Installation and Technical
9
INSTALLATION, CONT.
4. With the load cell cable routed into the enclosure, refer to Figure No. 4 and then remove
approximately 5 to 6 inches of the cable outer insulating jacket exposing the internal wires.
5. Next, cut the shield wire so that it extends past the outer jacket approximately 3/4 inch.
6. Now, remove 1/4 inch of insulation from the end of each of the four wires (without sense
leads) or six wires with sense leads.
7. Referring to the table below (or on the circuit board) for terminal connections, connect each
wire to terminal block P21. Refer to Figure No. 13 for terminal block location.
LOAD CELL CONNECTOR P21
PIN NO. Function PIN NO. Function
1 + EXCITATION 5 - SIGNAL
2 + SENSE 6 - SENSE
3 + SIGNAL 7 - EXCITATION
8. To terminate a wire, use a small flat blade screwdriver and press down on the release bar
for the terminal. Insert the wire into the opening and remove the screwdriver, allowing the
release bar to return to its original position, locking the wire in place. See Figure No. 5.
Figure No. 5
3/4 inch
Figure No. 4
5 to 6 inches
1/4 inch
Press
Down
Insert
Wire