Step 6—Bottom Closure Panel
These furnaces are shipped with bottom enclosure panel installed
in bottom return-air opening. This panel MUST be in place when
side return air is used.
To remove bottom closure panel, perform following:
1. Tilt or raise furnace and remove 2 screws holding front filler
panel. (See Fig. 25.)
2. Rotate front filler panel downward to release holding tabs.
3. Remove bottom closure panel.
4. Reinstall front filler panel and screws.
Step 7—Gas Piping
Gas piping must be installed in accordance with national and local
codes. Refer to current edition of NFGC in the United States.
Canadian installations must be made in accordance with NSCNG-
PIC and all authorities having jurisdiction.
Gas supply line should be a separate line running directly from
meter to furnace, if possible. Refer to Table 3 for recommended
gas pipe sizing. Risers must be used to connect to furnace and to
meter. Support all gas piping with appropriate straps, hangers, etc.
Use a minimum of 1 hanger every 6 ft. Joint compound (pipe dope)
should be applied sparingly and only to male threads of joints. Pipe
dope must be resistant to propane gas.
Table 2—Filter Information
AIR FILTER LOCATED IN BLOWER COMPARTMENT
FURNACE
CASING
WIDTH (IN.)
FILTER SIZE (IN.)
FILTER
TYPE
Side Return Bottom Return
17–1/2 (1) 16 X 25 X 1† (1) 16 X 25 X 1† Cleanable
21 (1) 16 X 25 X 1* (1) 20 X 25 X 1† Cleanable
24–1/2 (1 or 2) 16 X 25 X 1* (1) 24 X 25 X 1† Cleanable
* Filters may be field modified by cutting filter material and support rods (3) in
filters. Alternate sizes and additional filters may be ordered from your dealer.
† Factory-provided with furnace.
Fig. 23—Filter Installed for Side Inlet
A93045
FILTER
RETAINER
WASHABLE
FILTER
Fig. 24—Bottom Filter Arrangement
A00213
WASHABLE
FILTER
FILTER
SUPPORT
FILTER
RETAINER
17
1
⁄2-IN. WIDE
CASINGS ONLY:
INSTALL FIELD-SUPPLIED
FILTER FILLER STRIP
UNDER FILTER.
1″
24
1
/
2
″
3″
Fig. 25—Removing Bottom Closure Panel
A93047
BOTTOM
CLOSURE
PANEL
FRONT FILLER
PANEL