Step 6 — Install Field Insulation
When installing insulation at the jobsite, insulate the follow-
ing components:
• compressor motor
• cooler shell
• cooler tube sheets
• suction piping
• motor cooling drain
• oil reclaim piping
• oil cooler refrigerant side tubing
• refrigerant liquid line to cooler
NOTE: Insulation of the waterbox covers is applied only at the
jobsite by the contractor. When insulating the covers, make
sure there is access for removal of waterbox covers for servic-
ing. See Fig. 43.
CAUTION
Protect insulation from weld heat damage and weld splat-
ter. Cover with wet canvas cover during water piping
installation.
Fig. 43 — 19XR Insulation Area
a19-1563ef
a19-1564ef