REVIEW DRAFT—CISCO CONFIDENTIAL
3-26
Cisco 7500 Series Installation and Configuration Guide
OL-5008-03 B0
Chapter 3 Installing a Cisco 7500 Series Router
Installing the Cisco 7513, Cisco 7513-MX, and Cisco 7576
Step 4 Replace the card cage assembly. (See the procedure in the Installing the Card Cage Assembly section
on page 7-9.)
Step 5 Replace the power supplies. (See the Installing Cisco 7513, Cisco 7513-MX, and Cisco 7576 Power
Supplies section on page 3-27.)
Step 6 Replace the processor modules in the card cage. (See the procedure in Figure 3-14.) Check all ejector
levers and ensure the processor modules are securely installed; tighten any that are loose.
This completes the procedure for installing the Cisco 7513, Cisco 7513-MX, and Cisco 7576. Proceed
to the Attaching the Cisco 7513, Cisco 7513-MX, and Cisco 7576 Cable-Management Bracket section
on page 3-26.
Attaching the Cisco 7513, Cisco 7513-MX, and Cisco 7576 Cable-Management
Bracket
Use the following procedure to install the cable-management bracket. You will need a large flat-blade
screwdriver for this procedure.
Step 1 Locate the two slotted screws between the blower module and the card cage opening at the interface
processor end of the router. (See Figure 3-16.)
Figure 3-16 Installing the Cable-Management Bracket on a Cisco 7513, Cisco 7513-MX, and
Cisco 7576
Step 2 Loosen these two screws using the flat-blade screwdriver.
Step 3 Place the bracket over the screws, as shown in Figure 3-16.
Step 4 Tighten the screws.
122372
Loosen
screws (2)
Bracket
Blower
module