Wall jamb should be at here
16
15
INSTALLATION PROCEDURE / STEP 4
- 6 -
FOR ACRYLIC & FIBERGLASS SHOWER ENCLOSURES
Using a 1/8 inch drill bit, drill a hole about 1-1/2 inch deep at each
of the previously marked locations.
FOR TILED SHOWER ENCLOSURES
Using a 1/4 inch masonry drill bit, drill a hole about
1-1/2 inch deep at each of the previously marked locations.
Insert wall plugs into each of the drilled holes.
WARNING: Do not use wall anchors withberglass of acrylic
shower enclosures.
1/4”
16
38mm (#15)