CF65/75/85 series Removal and installation
PTO
4-1
4. REMOVAL AND INSTALLATION
4.1 REMOVAL AND INSTALLATION, ENTIRE DAF ENGINE PTO ON FLYWHEEL
HOUSING
Removing entire DAF engine PTO on
flywheel housing
1. If necessary, remove the prop shaft from the
PTO flange.
2. Remove the banjo bolts from the
engine PTO oil pipes.
3. If necessary, remove the electrical and air
connections of the engine PTO.
4. Remove the attachment bolts of the entire
PTO on the flywheel housing.
5. Remove the entire PTO from the flywheel
housing.
6. Remove the PTO centring ring dowel pins
from the flywheel housing.
Installing entire DAF engine PTO on flywheel
housing
1. Fit the PTO centring ring dowel pins in the
flywheel housing.
2. Install the entire PTO on the flywheel
housing.
3. Fit the attachment bolts and tighten them to
the specified torque. See “Technical data”.
4. Install the oil pipes and banjo bolts and
tighten them to the specified torque. See
“Technical data”.
5. If necessary, fit the electrical and air
connections of the engine PTO.
6. If necessary, fit the prop shaft on the
PTO flange.
7. Check the PTO operation.