7 | Piping installation
Installer reference guide
67
EGSAH/X06+10UDA9W
Daikin Altherma 3 GEO
4P598592-1A – 2019.12
▪ Thermostatic mixing valves. In accordance with the applicable legislation, it may
be necessary to install thermostatic mixing valves.
▪ Hygienic measures. The installation must be in compliance with the applicable
legislation and may require additional hygienic installation measures.
▪ Recirculation pump. In accordance with the applicable legislation, it may be
required to connect a recirculation pump in between the hot water end point
and the recirculation connection of the domestic hot water tank.
a Recirculation connection
b Hot water connection
c Shower
d Recirculation pump
7.1.2 Formula to calculate the expansion vessel pre-pressure
The pre-pressure (Pg) of the vessel depends on the installation height difference
(H):
Pg=0.3+(H/10) (bar)
7.1.3 To check the water volume and flow rate of the space heating circuit and brine circuit
The unit does not have an integrated expansion vessel, but a field supplied
expansion vessel can be installed in the brine circuit in case installing the brine
level vessel (delivered as accessory) is not optimal. For more information, see
"7.2.4To connect the brine level vessel"[469].
To make sure that the unit operates properly:
▪ You must check the minimum water volume.
▪ You might need to adjust the pre-pressure of the expansion vessel.
▪ You must check the total space heating water volume in the unit.
▪ You must check the total brine water volume in the unit.
Minimum water volume
Check that the total water volume per circuit in the installation is minimum 20litre,
the internal water volume of the indoor unit NOT included.
INFORMATION
If a minimum heating load of 1 kW can be guaranteed and setting [4.B] Space
heating/cooling > Overshoot (overview field setting [9‑04]) is 4°C, the
minimum water volume can be lowered to 10litre.
INFORMATION
In critical processes, or in rooms with a high heat load, extra water might be
required.