NOTE
When performing the test operation, always attach the decora-
tion panel. Otherwise, this may cause condensation.
CAUTION
After test operation is completed, check the items men-
tioned in Clause 2: (2) Items to be checked at time of
delivery on page2.
If the interior nish work is not completed when the test
operation is nished, for protection of the air con ditioner,
ask the customer not to operate the air conditioner until
the interior nish work is completed.
If the air conditioner is operated, the inside of the indoor
units may be polluted by substances generated from the
coating and adhesives used for the interior nish work
and cause water splash and leakage.
To the operator carrying out test operation
After test operation is completed, before delivering the
air conditioner to the customer, conrm that the control
box cover, the air lter and suction grille are attached.
In addition, explain the power supply status (power sup-
ply ON/OFF) to the customer.