Part 3. Commissioning Procedure
112 Design Guide DCM014A51
S1_Condensing Temperature
S2_Condensing Temperature
S1_Evaporating Temperature
S2_Evaporating Temperature
S1_Inverter Compressor 1 Speed
S2_Inverter Compressor 1 Speed
S1_Inverter Compressor 2 Speed
S2_Inverter Compressor 2 Speed
S1_Hot Gas Temperature
(Compressor 1)
S2_Hot Gas Temperature
(Compressor 1)
S1_Hot Gas Temperature
(Compressor 2)
S2_Hot Gas Temperature
(Compressor 2)
S1_Liquid Pipe Temperature
S2_Liquid Pipe Temperature
S1_Liquid Pipe Temperature
(HX Upper)
S2_Liquid Pipe Temperature
(HX Upper)
S1_Liquid Pipe Temperature
(HX Lower)
S2_Liquid Pipe Temperature
(HX Lower)
S1_Liquid Pipe Temperature (Deicer)
S2_Liquid Pipe Temperature
(Deicer)
S1_Gas Pipe Temperature
(HX Upper)
S2_Gas Pipe Temperature
(HX Upper)
S1_Gas Pipe Temperature
(HX Lower)
S2_Gas Pipe Temperature
(HX Lower)
S1_Compressor Suction Temperature
S2_Compressor Suction
Temperature
S1_Subcool Inlet Temperature
S2_Subcool Inlet Temperature
S1_Subcool Outlet Temperature
S2_Subcool Outlet Temperature
Note: Shaded points are not available by default and will need to be enabled during the iTM BACnet®
Server Gateway commissioning.