a. If the node joins the cluster successfully, the LCD displays the hostname of the node.
b. If the node fails to join the cluster, the LCD displays Failed to join. Return to Step 4.
c. To try another cluster, press Select.
Configure the Integrated Dell Remote Access
Controller
The integrated Dell Remote Access Controller (iDRAC) delivers advanced, agent-free local, and remote administration. iDRAC is
embedded in every F900, F600, and F200 node and provides a secure means to automate specific node management tasks. The
node management tasks include remote reboot or shutdown by using IPMI commands.
NOTE: Although iDRAC is preinstalled in F900, F600, and F200 nodes, caution is recommended when using iDRAC. Some
iDRAC features and functionality are accessible with the iDRAC interface, but are not supported. OneFS only supports the
following IPMI commands with the iDRAC interface:
Shutdown (power off)
Reboot (power cycle)
Startup (power on)
Power Status (read-only)
IDRAC does not require any additional software installation.
1. After connecting the network cables, and powering on the node, iDRAC is available for use. For iDRAC, the RJ-45 (1 GbE)
connects to the external network switch.
Figure 11. Node with RJ-45 iDRAC connection
2. Log in to iDRAC by using the following default username and password:
root
calvin
NOTE:
F900, F600, and F200 nodes can be ordered with both default username and password (root, calvin), or with
a random password option. If the nodes were ordered with the random password option, the username and password
differ.
Update the install database
After all work is complete, update the install database.
1. Browse to the Business Services portal.
2. Select the Product Registration and Install Base Maintenance option.
3. To open the form, select the IB Status Change option.
4. Complete the form with the applicable information.
5. To submit the form, click Submit.
F900 node configuration