Figure 10. Secure brackets to the rail (left hand rail shown for 2U)
1. Front rack post (square hole) 2. Rail location pins (quantity 2 per rail)
3. Left rail 4. Rear rack post (square hole)
5. Clamping screw (B) 6. Clamping screw (B)
7. Fastening screw (A) 8. 2U Ops panel installation detail (exploded view)
9. Left rail position locking screw 10. 2U enclosure fastening screw (C)
11. Key: Rail kit fasteners used in rack-mount installation
Install the 2U enclosure front bezel
Install the bezel if it was included with the enclosure.
While holding the bezel in your hands, face the front panel of the 2U12 or 2U24 enclosure.
1. Hook the right end of the bezel onto the right ear cover of the storage system.
Figure 11. Attach the bezel to the front of the 2U enclosure
2. Insert the left end of the bezel into the securing slot until the release latch snaps into place.
3. Secure the bezel with the keylock as shown in the detail view in Figure 11. Attach the bezel to the front of the 2U enclosure.
NOTE:
To remove the bezel from the 2U enclosure front panel, reverse the order of the previous steps.
Install the 5U84 enclosure
The 5U84 enclosure is delivered without the disks installed.
NOTE:
Due to the weight of the enclosure, install it into the rack without DDICs installed, and remove the rear panel
CRUs to decrease the enclosure weight.
The adjustment range of the rail kit from the front post to the rear post is 660 mm–840 mm. This range suits a one-meter deep rack
within Rack Specification IEC 60297.