Z9100–ON installation
To install the Z9100–ON system, complete the installation procedures in the order described.
Always handle the Z9100–ON and its components with care. Avoid dropping the system or its eld replaceable units (FRUs).
NOTE: ESD damage can occur if components are mishandled. Always wear an ESD-preventive wrist or heel ground strap when
handling the Z9100–ON and its components. As with all electrical devices of this type, take all the necessary safety precautions
to prevent injury when installing this system.
NOTE: For more information, see the
Open Networking Hardware Diagnostic Guide for the Z9100–ON System
.
Topics:
Unpack the Z9100-ON
Rack or cabinet hardware installation
Z9100-ON system installation
Ground cable
SFP+ optic installation
Port connectivity
Power up the system
Unpack the Z9100-ON
NOTE
: Before unpacking the system, inspect the container and immediately report any evidence of damage.
When unpacking the Z9100-ON switch, make sure that the following items are included:
One Z9100-ON switch
One RJ-45 to DB-9 female cable
Two sets of rail kits, no tools required
Two PSUs
Five fan units
Two country- and region-specic AC or DC power cords
Dell Networking Getting Started Guide for the Z9100–Open Networking (ON) System
Safety and Regulatory Information
Warranty and Support Information
Rack or cabinet hardware installation
You may either place the switch on a rack shelf or mount the switch directly into a 19" wide, EIA-310- E-compliant rack. Compliant racks
include four-post, two-post, or threaded. The Dell ReadyRails system is provided for 1U front-rack and two-post installations.
The ReadyRails system includes separately packaged rail assemblies.
CAUTION
: Your system is not NEBS Earthquake Z4-compliant if you use the 1U tool-less square-hole or two-post installation