Pre-Installation Installation Training
A70622-D1
105/192
Mounting step
The mounting procedure hereafter comes from instruction A70185 provided with tunnel with the
followed added recommendation:
1) It is recommended to mount input/ output plates (E) only after having cut the
openings for the products passage on the conveyor (step6/7)
2) It is recommended to use rubber tape for any cutting of polycarbonate sheet so as to
avoid any scouring and melting of the polycarbonate.
3) Recommendation to configure the tunnel installation in PLd safety level.
Step 1 : Mounting the main structure of
the tunnel (panels and transversal bars)
Step 2 : Mounting the door. . It allows access to the tunnel and
provides rigidity to the assembly.