10
Raise coil/conduit assembly up and rotate away from valve (B). Save spring washer under
coil.
B
Check valve retaining ring screws
Proportional valve retaining bracket
screws
NOTE:
Proportional valve bracket screws are no
longer than the two check valve retaining
screws.
Be sure to use the correct screws when
reinstalling.
11
For the far right meter only: To replace the far right meter (as viewed from side A), it will be
necessary to disconnect the product tube at the top of the outlet casting in order to get enough
flexibility to remove the tube from the proportional valve and access the valve retaining plate
screws.
12
Remove product tube lock pin from valve and remove tube from valve. (B)
13
Using a 10 mm open end wrench, loosen the (2) hex head screws securing the valve retaining
plate to the meter, and rotate retaining plate upward. (C) Note: On iMeter2, the two hex
socket head screws are on a diagonal, therefore, rotate the valve as needed to access one
of the screws at a time.
14
Pull valve out from meter (C) and rotate valve and conduit out and away from meter. (D)
15
Repeat steps 8-14 on opposite side.
WM048523 Rev 08 01/2019 317
18 iMeter2 Components Replacement Procedures