Repeat steps 8-11 on opposite side.
13
Remove (6) 5 mm Allen screws that secure the meter to the base. (For the two middle screws
use 5 mm on a drill bit socket with a 6” extension.)
14
Remove meter from side B of the dispenser.
15
Replace the three o-rings in the meter base.
16
Install the new replacement meter onto the base and secure with the (6) 5 mm screws.
17
Replace o-ring on the valve.
18
Reinstall valve into meter and secure the valve retaining plate. (Be sure to seat the retaining
plate properly into the groove on the valve so that the o-ring is not pinched.)
19
Ensure that magnet washer on the conduit is pushed up against the bottom of vapor barrier
as shown in Fig 6.10.
20
Replace the product tube o-ring.
21
Reinstall the product tube into the valve and secure the tube with the retaining pin. Be sure
the pin snaps in place.
22
Repeat steps 17-21 on opposite side.
23
Reinstall WIP.
24
Clean and reinstall the strainer and install new filter. (Remotes).
25
Turn power on to dispenser and submersible pump.
26
Reset the emergency shear valve.
27
Run test sales to clear air from lines and check for leaks.
28
Perform Meter Verification Accuracy and Calibration procedure as required and seal me-
ter/pulser. See the Meter Calibration section in this manual.
Figure 6.11: Meter with Valve rotated
90 WM048523 Rev 08 01/2019