NM2C PMS PROCEDURE (continued)
( ) 6.11.2 Cylinder Gauges
6.11.2.1 Are the pressure gauges correct for the gases indicated by the
flowmeters? ___ (Y)
6.11.2.2 Is the gauge closest to the table top for cylinder supply pressure?
___ (Y)
6.11.2.3 Bleed all pressure from the cylinder circuit.
6.11.2.4 Are the cylinder gauges at zero (0) PSI? ___ (Y)
6.11.2.5 Open the cylinder valves.
6.11.2.6 Do the cylinder pressure gauges respond properly? ___ (Y)
( ) 6.11.3 Pipeline Gauges
6.11.3.1 Are the gauges right below the flowmeters for pipeline supply
pressure? ___ (Y)
6.11.3.2 Are the pipeline pressure gauges at zero (0) PSI? ___ (Y)
6.11.3.3 Connect the pipeline supply.
6.11.3.4 Do the pipeline pressure gauges respond properly? ___ (Y)
6.11.3.5 Are the correct gas identification labels affixed at each of the
pipeline inlets? ___ (Y)
6.11.3.6 Does the back panel identify each of the pipeline inlets properly?
___ (Y)
6.11.3.7 Disconnect the pipeline hoses.
Rev. K