600 A 35 kV Class T-OP II connector assembly installation instructions
2INSTALLATION INSTRUCTIONS MN650051EN May 2017
Tools
1/2” Wrench
Torque Tool (Catalog Number TQHD635)
5/16” T-Wrench (Catalog Number TWRENCH)
O & T Tool (Catalog Number OT635)
Combined O & T/Torque Tool (Catalog Number OTTQ635)
ote:N If a Combined O & T/Torque Tool is used, a separate
O & T tool and torque wrench is not required.
Prepare the cable
ote:N If concentric neutral cable is not being used, follow
cable preparation directions in shield adapter kit.
Step 1
Train cable
Position cable vertically so that it is centered between
apparatus bushing and parking pocket, parallel to, and 7”
(178 mm) from apparatus frontplate.
Provide adequate cable slack for cable movement
between standoff bushing and apparatus bushing.
Support cable as needed to maintain position.
Cut cable 1 3/4” (45 mm) from centerline of bushing.
(Refer to Fig ure 2.)
BUSHING
CABLE
1 3/4"± 1/4"
(45mm ± 7 mm)
7"
(178 mm)
Figure 2. Line illustration for cable training
Step 2
Remove concentric neutral wires or jacket
ote:N Care should be taken to not cut or score the neutral
conductors when cutting the cable jacket.
Measure 13” (330 mm) from end of cable.
(Refer to Figure 3.)
If jacketed neutral cable, remove jacket to
13” dimension.
If unjacketed neutral cable, bind neutral wires using
(3) wraps of tape at 14 3/4” dimension.
Pull back concentric neutral wires. Allow enough
extra concentric neutral wires to connect to ground
after installation and allow movement to insulated
standoff bushing.
1 3/4” ± 1/4"
(45 mm ± 7 mm)
13”± 1/4"
(330 mm ± 7 mm)
BUSHING
CABLE
CONCENTRIC
NEUTRAL WIRES
Figure 3. Line illustration of removing concentric
neutralwires
Step 3
Remove insulation shield.
Remove insulation shield 10 1/2” (267 mm) from end of
cable. (Refer to Figure 4.)
ote:N Do not cut or nick insulation.
10 1/2" ± 1/8"
(267 mm ± 3 mm)
1"
(25 mm)
TAPE MARKER INSULATION SHIELD
INSULA
TION
Figure 4. Line illustration of cable stripback
Step 4
Put tape marker in place
Measure 1” (25 mm) from end of insulation shield.
(Refer to Figure 4.)
Wrap two turns of tape to serve as marker for cable
adapter location.
Step 5
Remove conductor insulation
ote:N Do not pencil cable.
Remove insulation exposing bare conductor to length of
4 3/8” (111 mm). (Refer to Figure 5.)
ote:N Do not unwind conductor strands.