Chapter 6 Stabilizing the UPS
NOTE The stabilizing bracket is optional.
NOTE The location for the stabilizing bracket shown in Figure 14 is the only acceptable
location on the equipment frame for anchorage.
NOTE For seismic applications, use suitable floor bolts to attach the UPS to the flooring.
It is recommended to use 0.3125” (7.94 mm) self-drill bolts and hardware with 1.3125”
(33.34 mm) minimum embedment for 3000PSI-strength concrete. Refer to your local building
codes for seismic requirements. See Figure 15 for the floor bolt pattern.
To stabilize the UPS:
1. Lower the leveling feet to prevent the UPS from rolling.
Figure 13. Lowering the Leveling Feet
2. Attach the stabilizing bracket to the bottom of the UPS rear panel
using the retained hardware from the shipping pallet (see
Figure 14).
3. Use the holes and slots in the bottom of the bracket to attach the
UPS to the flooring if desired.
4. Continue to “Internal Battery Installation” on page 33 or
“Ultracapacitor Module Installation” on page 45.