TIE CABINET INSTALLATION
Eaton 9355 Tie Cabinet (20/30 kVA) Installation Guide S 164201630 Rev D www.eaton.com/powerquality
14
21. Hardwire the load to the Tie Cabinet (see Figure 8).
Neutral
Line 1
Ground
Line 2
Line 3
Maintenance Bypass
Wiring to UPS TB4
Figure 8. Load Connections