44 Eaton 9395XC UPS 1200kW/1200kVA, 1350kW/1350kVA or 1500kW/1500kVA 164001079—Rev 01
Figure 17. Removing the ISBM/PM Section Right Side Shipping Bracket
Pallet
Right Side Shipping
Bracket
Shipping Bracket
Bolts
Shipping Bracket
Bolts
Front Door
4. Using a forklift (see the caution statement at the beginning of this procedure), raise the cabinet until the
cabinet bottom clears the pallet by approximately 3 mm (1/8”) (see Figure 20.
5. Pull the pallet from under the cabinet. Discard or recycle the pallet and shipping brackets in a responsible
manner.
6. Carefully lower the cabinet until the cabinet base contacts the floor.
7. Repeat Steps 2 through 6 for the I/O cabinet (see Figure 18 and Figure 19
UPS System Installation

Table of Contents