58 Eaton 9395XC UPS 1200kW/1200kVA, 1350kW/1350kVA or 1500kW/1500kVA 164001079—Rev 01
5. Using hardware from the external wiring terminal hardware kit (see Table 9), connect phase A, B, and C
wiring from the output terminals the UPS unit to the customer-supplied tie cabinet or load distribution
panel. See paragraph 3.2.4 UPS System Power Wiring Preparation UPS System Power Wiring Preparation
for wiring and termination requirements.
6. Proceed to paragraph 4.6.2 Battery Power Wiring.
7. Using hardware from the external wiring terminal hardware kit (see Table 9), connect phase A, B, and C
power wiring from output terminals (E9, E10, E11) to the critical load. See paragraph
3.2.4 UPS System Power Wiring Preparation for wiring and termination requirements.
8. Proceed to paragraph 4.6.2 Battery Power Wiring.
Figure 29. I/O Section Power Terminal Locations
{
AB
AB
DC Input from
Battery Input (+), E4
Battery Output (-) E5
I/O FRONT
UPS Input, E1/E2/E3
(See gure UPS
Power Terminal Detail BB)
Bypass Input: E6, E7, E8
UPS Output: E9, E10, E11
(See gure UPS
Power Terminal Detail AA)
{